Construction productivity

Construction Productivity Reference Sheet

Construction Productivity Reference Sheet

Excavation & Earthwork

  • Manual Excavation ➔ 1.5 – 2.0 m³/labour/day
  • By JCB ➔ 60 – 80 m³/hour
  • By Poclain (200) ➔ 100 – 1500 m³/hour
  • Roller Compaction ➔ 200 – 250 m³/day

Concrete Works

  • Manual Mixing ➔ 1.5 – 2.0 m³/labour/day
  • Manual Laying ➔ 3 – 4 m³/labour/day
  • Pump Placement ➔ 20 – 30 m³/hour
  • Curing (ponding) ➔ 1 labour per 100 m²
  • Shuttering ➔ 1.2 – 1.5 m³/labour/day

Reinforcement Work

  • Cutting, Bending, Tying ➔ 100–150 kg/labour/day
  • Fixing (Columns/Beams) ➔ 80–120 kg/labour/day
  • Fixing (Slabs/Footings) ➔ 100–150 kg/labour/day

Masonry

  • Brick Masonry (manual) ➔ 0.2 – 0.25 m³/labour/day
  • Brick Masonry (machine mixing) ➔ 0.3 – 0.4 m³/labour/day
  • AAC Block Masonry ➔ 0.5 – 0.7 m³/labour/day

Plastering & Finishing

  • 12mm Plaster ➔ 8 – 10 m²/labour/day
  • 20mm Plaster ➔ 6 – 8 m²/labour/day
  • Putty ➔ 12 – 15 m²/labour/day
  • Painting (1 coat) ➔ 15 – 20 m²/labour/day

📌 These values serve as general guidelines. Actual productivity may vary based on site conditions, labour skill, weather, and equipment used.